|
2007 District
Asset Protection Project Photos--Your Tax Dollars Hard at Work!
The
following are some "progress" photos taken at some of our schools
that underwent renovation work that began in the summer of 2007.
All of the projects are substantially completed, with the interior
projects finished. The only work that remains is outside work
(landscaping/roofing) that will be completed when the weather
improves. |
|
NEIL
ARMSTRONG MIDDLE SCHOOL
STATUS: All of the interior work is
completed.
Landscaping will be completed when the
weather is better. |

Lighting in the Neil
Armstrong auditorium is being upgraded.
|
|
New carpeting has
been installed in several areas at Neil.
|
|
|

Excavation and drainage
work is being completed. |
|
|
|

These pictures were
taken eight days after the photos shown above and show the progress
on the excavation/French drain work at Neil Armstrong. |
 |
 |
|
 |
|
 |
|

These next four pictures
were taken 8 days after the previous group and show work on the
auditorium lighting upgrades at Neil Armstrong as well as the
drainage/excavation work being done. |
 |
 |
|
|
|
 |
|
|

This next group of
pictures was taken one week after the previous group and shows work
on the auditorium lighting and excavation/drain work being done at
Neil. |
 |
 |
|
 |
 |
 |
|
|
|
 |
|
|

These next six pictures
were taken 15 days after the previous group. As you can see,
the lighting upgrades in the Neil auditorium are almost finished! |

Excavation/drainage work
at Neil continues. |
 |
|
 |
 |
 |
|

These pictures were
taken two weeks after the previous group and show that the work on
the auditorium and excavation/drainage work are almost complete.
Principal Janet O'Rourke reports that everything should be completed
in a week or two. Thank you to everyone for their patience! |

More auditorium shots.
You can see there are more lights in the ceiling than ever before! |
 |
|

The drainage holes have
been filled and the work is almost complete. |
 |
 |
|
 |
The lighting upgrades in
the auditorium are completed. The contractor has to complete
some minor cleaning projects and then the auditorium with be
available for use.
These are the last of
the Neil renovation photos! Thanks to everyone for their
patience throughout the process! |
 |
|
|
|
|
|
|
|
FRANKLIN ELEMENTARY SCHOOL
STATUS: All of the interior work is
completed.
The students are using the new music, speech and language and
instructional support classrooms. Outdoor
seeding/landscaping/paving will be completed when the weather
permits. |

The modular classrooms
at Franklin are in the process of being removed and will be replaced
with four classrooms, created from reconfigured space within the
school.
|
Two Special
Education Classrooms are being created in the area near the
current gymnasium and two Music Classrooms will be constructed
in the space below the gymnasium.
|
Here's another view
of the two new Special Education Classrooms.
|
|

These pictures were
taken eight days after the above photos and show progress in the two
Special Education Classrooms that are being created near the
gymnasium. |
 |
 |
|

Here is a photo looking
down the left hand side of Franklin toward the new music classrooms
that are being constructed underneath the gymnasium. |

The following pictures
show the excavation/French drain work that is being done on the
right hand side of Franklin, past where the modular classrooms
currently sit. |
 |
|
|
|
 |
|
|

The next nine
photographs were taken 8 days after the previous group. The
next two photos show progress on the construction of two of the four
new classrooms at Franklin. These two are next to the
gymnasium. |
 |

The next four photos
show the drainage work has been completed. Landscaping is the
next step. |
|
 |
 |
 |
|
 |

Construction materials
wait in the back parking lot. |

Two new classrooms are
being constructed below the gym at Franklin. |
|

This next group of
photos was taken a week after the previous group. The next
three photos show progress on the new classrooms by the gymnasium. |
 |
 |
|

As you can see, we're
waiting for grass to grow in the area where the new drains were
installed. |
 |
 |
|

We're waiting for grass
to come up at the visitors parking area. |
|

An updated exterior shot
of the two classrooms being constructed underneath the gym. |
|

These next six photos
were taken 15 days after the previous group. These next three
photos show the progress on one of the two new upstairs classrooms. |
 |
 |
|

These next two photos
show the painting that is being done in the other new upstairs
classroom. |
 |

As you can see, there is
much work to be done on the two classrooms being created underneath
the gymnasium. |
|

Work is progressing on
the two new classrooms for Speech and Language and IST. |
 |
 |
|
|
|

The biggest change is
the progress on the new music classrooms to be located underneath
the gymnasium. A concrete floor has been poured and walls are
being erected. |
|
|

These next set of
pictures were taken three weeks after the previous group and show
progress on the four new classrooms that are being configured out of
existing space at Franklin. |

These rooms are being
built next to the gymnasium. |

These new classrooms
were locker rooms and are being converted to to classroom, bathroom
and smaller locker space. |
|
 |
 |

These next three
pictures show progress on the rooms being created under the
gymnasium to serve as music classrooms. |
|
 |
|
 |
|

This next group of
photos was taken three weeks after the previous group and will show
that the construction of the new classrooms at Franklin are almost
complete! |

When you come down the
stairs at Franklin, these are the doors leading to the new music
classrooms that are constructed underneath the gymnasium. |

Here is one of the new
music classrooms. |
|

Here is the other new
music classroom. |

This is the view of the
two new music classrooms from outside their doors. |

This is the new
Instructional Support classroom constructed upstairs. |
|

This is the new ladies
restroom located upstairs. |
|

Here is the new Speech
and Language upstairs classroom. It looks empty without
students! |
|

The next five photos
were taken on Monday, December 10, and show the ribbon cutting
ceremony to officially open the new music classrooms at Franklin! |

The furniture is in the
music classrooms and ready for students! |

Mrs. Alstad's strings
students love their new music classroom! |
|

All Franklin students
had the opportunity to take a quick tour of their new classroom
spaces. |
This concludes the
Franklin renovation photos. |

Students are ready to
move into their new Speech and Language classroom! |
|
|
|
|
|
|
|
MEMORIAL ELEMENTARY SCHOOL
STATUS: The interior
addition is completed and the students began to occupy the new space
on Monday, February 18. Roof and landscaping projects will be
completed when the weather improves. |
 The modular
classrooms at Memorial are in the process of being removed and will
be replaced with a new four-classroom addition, which can be seen
from the Faculty Room window, looking out toward the playground
area.
|
Here's a shot of the
area that is being excavated for the addition. |
Here's another view
of the area. |
|
 |
 |

Foundation drain work is
also being done at Memorial. |
|
 |
 |

Memorial is also
receiving a new roof this summer. |
|
|
|

Another shot of the roof
at Memorial.
|
|
|

These photos were taken
eight days since the ones above. The next five shots are of
the new four-classroom addition that is being built at Memorial to
replace the modular units. |
 |

Here you can see
concrete being poured into the foundation footer for the new
addition at Memorial. |
|
 |
 |

These next two pictures
show the progress on the new roof installation at Memorial. |
|
|
|
 |
|
|

The following eight
pictures were taken 8 days after the previous group. These
next four pictures show progress on the four classroom addition that
is being constructed at Memorial. |
 |
 |
|
 |

Here's a look at the
drainage work being done around Mr. Chalus' office. |

Work on the roof is
almost done! |
|
 |
|
 |
|

Here's an exterior shot
of the addition at Memorial if you're looking from South Park Road.
This next group of
shots were taken a week after the previous group. |

Inside the school a
temporary wall has been constructed outside the faculty room to keep
the construction noise/dust to a minimum. |

Another shot of the
temporary wall that will keep students away from the construction
area. |
|

More shots of the
addition. |
 |
 |
|

More shots of the new
roof. |
 |
 |
|

The next seven pictures
were taken 15 days after the previous group. The next four
pictures show the progress on the 4-classroom addition at Memorial. |
 |
 |
|
 |

Work on the roof is
progressing. |
 |
|
|
|
 |
|
|

These next 10 pictures
were taken 22 days after the previous group and show progress at
Memorial. The above picture shows that work is almost
completed to remedy drainage issues around the principal's office. |

These next seven photos
show the progress on the four-classroom addition. |
 |
|
 |
 |
 |
|
 |
 |

Work on the roof is
almost complete. Work will begin again when the roof for the
new addition is ready to be installed. |
|
|
|
 |
|
|

This next group of
pictures was taken three weeks after the previous group and show
progress on the four-classroom addition at Memorial. |
 |
 |
|
 |
 |
 |
|
 |
|

The majority of the roof
work has been completed. Anything that has not been
completed to date will be completed when the roof for the new
addition is installed. |
|

This next group of
photos was taken three weeks after the previous group and you can
see that the exterior work on the new Memorial four classroom
addition is coming along! |
 |
 |
|

This is going to be the
new custodial area for the building. |

Here are the new
classrooms. |
 |
|
 |

Exterior shots from the
back of the school. |
 |
|

These pictures were
taken a week after the previous group and show the exterior of the
new edition shaping up. |
 |

Much work still needs to
be done on the interior. |
|

These next five photos
were taken a couple of days before winter recess and show that great
progress has been made on the new addition at Memorial. This
photo shows that tar paper is on the roof and that work will be
completed soon, weather permitting. |

Concrete floors have
been poured and the ceiling is being installed. |
 |
|
 |
 |
 |
|

These next seven photos
were taken the second week in January and show the progress that has
been made over the past two and one-half weeks. |

If you look at the photo
that is two above this one, in the same column, you will see that
the view has changed drastically. A hallway has been created,
with the new rooms located on both sides of the hallway. |

This is a picture of
Mrs. Sudnik's new third grade classroom. |
|
 |

The new custodial
storage room. |

One of the new fourth
grade classrooms. |
|
|
|

Another fourth grade
classroom. |
|
|

These next six pictures
were taken the third week of January and show progress is being made
on the new classrooms. Pictured above is a shot of the new
lockers. |

Wiring is being
completed. |

These next four shots
show the new classrooms. |
|
 |
 |
 |
|

These next seven shots
were taken February 8 and show that the new rooms at Memorial are
ready to occupy, once the district receives permission from the
authorities to occupy the space. As you can see from this
photo, the temporary wall in the Memorial hallway has been removed
and you can see the corridor of the new edition at Memorial. |

This is the
Instructional Aides' Room. |

This is Mr. Kovach's new
Custodial Storage Room |
|

The next three photos
show the new Fourth Grade Classrooms are ready to be occupied. |
 |
 |
|
|
|

This is Mrs. Sudnik's
new Third Grade Classroom. |
|
|

There's a smiley face on
the window in one of the new Memorial classrooms. We're happy
the edition is completed enough for students to occupy! |

Landscaping and the roof
will be completed when the weather improves. |

The new hallway leading
to the new classrooms at Memorial. |
|

The new Aides' Room. |

Mr. John has a new
custodial room. |

Mrs. Sudnick's third
grade classroom. |
|

Mrs. Reese's fourth
grade classroom. |

Miss Mancinelli's fourth
grade classroom. |

Mrs. Hruby's fourth
grade classroom. |
|
|
|

The new faculty room. |
|
|
|
|
|
|
|
|
LINCOLN ELEMENTARY SCHOOL
STATUS: Students moved out of the modular classrooms and into their new
classrooms located inside Lincoln on December 3. Landscaping
work will be completed when the weather improves. |

The modular classrooms
at Lincoln are in the process of being removed and replaced by a
four-classroom addition at the back of the school. Here is a
view from the parking lot, looking down the side of the building. |
The next three
pictures take a closer look at the beginning phases of
construction.
|
|
|
 |
|

Lincoln is also getting
a roof replacement this summer. |
|
|

The following photos
were taken eight days after the previous photos. Here is a
shot of the four-classroom addition which is being built behind
Lincoln. |

If you compare this
photo to the similar one taken eight days ago, you can see the
progress that is being made on the addition at Lincoln. |

Another shot of the
classroom addition at Lincoln.
|
|

Bulldozers are
excavating the ground behind Lincoln to accommodate the new
addition.
|

The next shots show
progress on the new roof at Lincoln.
|
 |
|
| |

|
|
|

This next set of
pictures was taken 8 days after the previous group. The next
two pictures show an updated view of construction, looking down the
right side of Lincoln toward the playground. |
 |

A view of the work going
on behind Lincoln to create four new permanent classrooms to replace
the modular classrooms. |
|
 |
 |
 |
|

The roof work at Lincoln
contines. |
|
 |
|

This next group of
pictures was taken a week later than the last group. These
next few pictures show the progress on the new addition. |
 |
 |
|
 |
 |
 |
|
 |
 |
 |
|

Roof work continues. |
|
 |
|

These next seven
pictures were taken 15 days after the previous group. The next
five photos show progress on the new four-classroom addition that is
being constructed behind Lincoln. |
 |
 |
|
 |

Here's a view from the
inside-out. |

Work on the Lincoln roof
continues. |
|
| |
 |
|
|

These next nine pictures
were taking two weeks after the previous group and show progress on
the new addition. |
 |
 |
|
 |
 |
 |
|
 |
 |

Final completion of the
roof has temporarily been put on hold in anticipation of the roof
being ready for the new addition. |
|

The next six pictures
were taken three weeks after the previous set. As you can see,
drainage work begins along the side of Lincoln. |

The outside of the
four-classroom addition has been bricked.
|

Here are some more views
of the addition exterior. |
|
 |
 |

A close up of the
drainage work at Lincoln. |
|

This next group of
pictures was taken Thanksgiving week and will show tremendous
progress on the edition at Lincoln. |

These next three
pictures are of the new fourth grade classrooms. |
 |
|
 |

This is the new Reading
Classroom. |
 |
|

This is a new storage
room located on the downstairs level. |

Here are the new doors
leading to the outside of Lincoln from the downstairs level. |

This is the new
retaining wall located outside the back of Lincoln. |
|

This next group of
photos was taken two weeks after the previous group and show that
the new addition at Lincoln is almost complete! |
 |
 |
|
 |

Here are some shots of
the new fourth grade classrooms. |
 |
|
 |

The new Reading
Specialist Classroom. |

New lockers. |
|

The emergency exit on
the lower level. |

A new storage room on
the lower level. |

The new Music Classroom. |
|
| |

Another shot of the
Music Room. |
|
|

Here are the modular
units some of the Lincoln students were learning in until their new
classrooms were finished. |

The following pictures
were taken on Monday, December 3 and show the students in their new
classrooms located inside Lincoln. |

The students like their
new rooms, describing them as "bigger and better," "nicer,"
"better," "warmer" and "awesome." |
|
 |
 |
 |
|
| |
This concludes our
construction pictures for Lincoln. Thanks to everyone for
their patience during the construction process. |
This concludes the
Lincoln progress photos! |
|
| |
|
|
|
|
WILLIAM PENN ELEMENTARY SCHOOL
STATUS: Roof and electrical work completed. |

Electrical upgrades are
being made to William Penn.
|

A new roof is being installed at William Penn. |
|
|

These next three
pictures were taken 8 days after the previous group and show
progress on the roof at William Penn. |
 |
 |
|

These next four photos
show electrical upgrades to William Penn classrooms. |
 |
 |
|
 |
|

Work will continue on
the roof. |
|

These next three
pictures were taken 15 days after the previous group and shows work
progressing on the William Penn roof. |
 |
 |
|

These next three
pictures were taken 12 days after the previous group and show the
progress on the William Penn roof. |
 |
 |
|
|